Change requests

Review and approve
ETRM: Eine Änderung umsetzen – vom Change Request über die Artefaktseite bis zum Review
The video is narrated in German; you can switch on subtitles in the player. Playing the video connects to YouTube (Google). More in the privacy policy · Watch on YouTube

Once a state has been agreed with the customer and recorded as a baseline, changes should not simply happen but be decided deliberately. This is what change requests (CR) are for.

Change request with affected artifacts and impact via links

Process

Step Who What
1. Request role COMMENT and above title, description of the change, reason or trigger, affected artifacts and the reference state (baseline). The group admins are notified.
2. Assess everyone The request automatically lists all artifacts connected to the affected ones via links (up to two steps), with their distance. This is the basis for effort and risk.
3. Decide group admin Accept or Reject, with a note. The person who submitted the request is notified.
4. Implement role EDIT and above Change the affected artifacts. Dependent links become suspect and must be checked. Then Mark as implemented.
5. Prove everyone Comparing the new baseline with the reference state shows exactly what has changed.

Submitting a request

  • On the artifact page with Request change: the artifact is then already entered as affected.
  • Or via Change requests → New change request in the project overview.

Each request receives a consecutive number in the project (CR-1, CR-2, …). The list shows all requests with their state: requested, accepted, rejected, implemented.

Interaction with other functions

  • Suspect links show during implementation which derived requirements and test cases have to be followed up (Traceability).
  • The metrics count open requests and accepted requests not yet implemented (Metrics).
  • After implementation, a review of the changed artifacts and a new baseline are recommended.

Example from the sample project: CR-1 “Reduce high-power charging time from 20 to 18 minutes” concerns one stakeholder and one system requirement. The impact covers seven further artifacts, including the fast charging test case and a safety goal.